Regulators in Wallonia and a Virginia judge halted two Google projects within days, citing a revoked permit and an open-government violation
Sun 29 Nov 2026 · 14:35 EST · 3 min read
In Regulation
Share
Google has been ordered to stop construction twice in under a week, on two different continents. On Thursday, inspectors in Belgium’s Wallonia region ordered about 300 workers off a Google data center site in Farciennes, near Charleroi.
Three days before that, a Virginia judge froze construction at a separate Google campus in Botetourt County.
A revoked permit and a site that kept humming
The Belgian dispute is over a 30,000 m² facility that was nearly finished when inspectors arrived. The core issue is a water-cooling permit.
That permit was temporarily approved in April 2026, then revoked in August 2026. According to Wallonia’s regional government, Google kept building after its amended permit was pulled.
The inspection took place on November 26-27, 2026. It followed evidence of compliance issues supplied by Greenpeace Belgium, so an environmental group was the tipster that set the enforcement in motion.
Google responded that it had paused the work “pending additional guidance.” It also said it would seek clarity on what its compliance obligations in Belgium are.
The next formal checkpoint is a Council of State hearing on the Belgian appeal, scheduled for January 7, 2027.
The crypto and markets news you actually need—every morning.
Daily. Free. Join 34,000+ readers across crypto, finance, and policy.
We respect your privacy. Unsubscribe anytime.
Virginia’s transparency problem
The Virginia case has nothing to do with water. It is about how a deal got approved.
On November 23, 2026, a circuit court judge ruled that the performance agreement for Google’s planned $3 billion data center in Botetourt County violated Virginia’s Freedom of Information Act. The judge found that county supervisors broke the state’s open-government law when they signed off on the arrangement.
Construction at the site had already started in September 2026. The ruling halted it, with only limited wind-down activity continuing.
Hearings related to these matters are scheduled for early 2027, so neither project will get back to full speed quickly.
Why Belgium and Virginia matter to Google
Google is not new to Belgium. It opened its first European data center in Saint-Ghislain, Belgium, in 2007, and the country has been a base for its European infrastructure since.
Water is the flashpoint. Critics of the Farciennes project have pointed to an existing Google facility that uses about 1 billion liters of water annually.
What this means for the data center buildout
The objections fall into three categories: water extraction, energy use, and procedural transparency. The Belgian case is about water. The Virginia case is about transparency.
The January 7, 2027 Council of State hearing in Belgium will show whether Google can save the Farciennes permit or has to change how the facility is cooled.
In Virginia, the question is whether Botetourt County reruns its approval process in the open, and how quickly. If the deal is re-approved properly, the delay may be temporary; if public scrutiny changes the terms, the project could look quite different when construction resumes.
Disclosure: This article was edited by John Chen. For more information on how we create and review content, see our Editorial Policy.