Brussels (Belgium) (AFP) - The American giant Google announced this Saturday that it has paralyzed the construction works of one of the large data centers it plans in the south of Belgium, following a court decision motivated by the lack of permits.
First modification: 11/28/2026 - 13:29
"We have suspended the works, in accordance with the guidelines of local authorities and awaiting further indications," a Google spokesperson told AFP.
The Belgian authorities announced on Friday that they had forced Google to suspend the works after an alert from the organization Greenpeace due to the lack of permits.
This is a data center that is being built in a business park that extends across three municipalities in the Charleroi region (south), on a former mining site of about 50 hectares.
Nicolas Yernaux, spokesman for the regional authorities of Wallonia, confirmed to AFP on Friday that a "stoppage order" had been issued due to the "illegal construction" of a three-hectare building in recent weeks on the site.
Work on Google began after the authorities granted a construction permit in 2024.
The request also sought to authorize a cooling system for the IT facilities that used water extracted from the Sambre River, despite the fact that the initial project contemplated air cooling.
Google's plans to build mega data centers for artificial intelligence (AI) have already encountered obstacles in several countries.
A month ago, the Finnish police announced the opening of a criminal investigation into the environmental impact of preparatory work at a planned site for Google in Muhos (northern Finland).